BOI introduces quarterly project progress reporting requirement
Previously, BOI-promoted companies were required to submit progress reports only twice a year, in February and July. The new requirement replaces the semi-annual reporting schedule with quarterly reporting to enable the BOI to monitor project implementation more effectively and to improve transparency and compliance throughout the investment period.
Reporting schedule
| Reporting quarter | Period covered | Submission deadline |
| Quarter 1 | January - March | By 30 April |
| Quarter 2 | April - June | By 30 July |
| Quarter 3 | July - September | By 30 October |
| Quarter 4 | October - December | By 30 January (of the following year) |
Failure to submit the required Project Progress Report within the prescribed deadline may result in significant consequences for the promoted company, including:
- Suspension of BOI Incentives: The BOI may suspend the company’s tax and non-tax incentives until the reporting obligation has been fulfilled.
- Impact on visa and work permit for expatiate employee: Non-compliance may affect the processing of BOI-related applications, including position approvals, visa extensions, and work permit renewals for foreign executives, experts, and skilled employees.
- Revocation of BOI promotion: If the company fails to submit the required reports for two consecutive reporting periods, the BOI may consider revoking the investment promotion certificate.
As the BOI increases its focus on monitoring ongoing investment projects, timely reporting is becoming more important than ever. Companies should take proactive steps to ensure compliance and safeguard the valuable incentives and benefits granted under their BOI promotion.
References (in Thai):
- Announcement of the Board of Investment No. 8/2026 Re: Conditions for the submission of quarterly actual investment reports. Retrieved from Thailand Board of Investment.